Weinviertel Energy Hub Expands: Construction Work at the Spannberg Substation in Full Swing

APG and Netz Niederösterreich Report Positive Interim Results

Visible progress at the construction site

“Despite challenging conditions, including an exceptionally heavy rainstorm in August and last summer’s record-breaking heat, we have managed to stay on schedule,” reports Christof Schweer, who is overseeing the construction of the 380-kV section on behalf of APG. The first partial commissioning of the new Weinviertel substation is scheduled for late 2028, with full completion planned for mid-2029. “Progress is now clearly visible across the construction site. Major developments include the extensive site preparation work, the construction of the transformer foundations and associated firewalls, and the striking retaining wall along the southern boundary. Stretching approximately 250 meters, the wall reaches a height of around eleven meters,” the project manager explains. Work has also begun on the operations building and an internal access road.

Key construction phases already completed

Since construction began, the project has already reached several major milestones. On the APG side, these include the new access road to the substation, including a bridge over the Sulzbach river, the 600-m³ firewater tank for the transformer fire-extinguishing system, and a substantial portion of the earthworks. The technically challenging specialist civil engineering work and much of the foundation work for the line portals have also been completed. “The line portals will connect the new substation to the 380-kV Weinviertel transmission line, which runs past the site. This line has been in operation since summer 2022 and will provide a direct link between the new facility and Austria’s nationwide transmission grid. This will significantly improve security of supply and local grid resilience,” explains Schweer.

“Construction progress is also clearly visible in the Netz NÖ section of the facility,” says Besim Demiri, Netz NÖ project manager responsible for the 110/30-kV section. He reports: “Work is progressing according to plan, and several key construction milestones have already been reached. The switchgear building has been completed, as have the foundations for all six planned 110/30-kV transformers, the line portals and the lightning protection towers. The approximately 390-meter-long fence and retaining wall along the northern and western boundaries of the site have also been comp         leted.”

With earthworks largely completed in both sections of the facility, construction-related traffic at the site has already begun to decrease noticeably.

Upcoming heavy hauls: first large transformers to arrive in Spannberg soon

“A major milestone is just around the corner,” says Schweer. “In December and January, the first two 380/110-kV large transformers will be delivered. Each weighs around 290 tons and measures approximately 11 meters in length, 4 meters in width and 4.6 meters in height.”

The final leg of the journey, from Dürnkrut railway station to the construction site in Spannberg, will involve a spectacular heavy-haul road transport operation. A third 380/110-kV transformer is scheduled for delivery in the first half of 2028.

Demiri adds: “The first two 110/30-kV transformers are scheduled for delivery in spring 2027, followed by four more in autumn. Each weighs approximately 90 metric tons. Completion of the Netz NÖ section of the project remains on schedule for autumn 2028.”

Major construction project with regional economic impact

Around 60 people are currently employed at the APG construction site. To date, more than 200,000 cubic meters of earth have been moved, approximately 5,000 cubic meters of concrete poured and around 540 tons of structural steel used. Numerous services are being provided by regional companies, and construction materials are also sourced locally wherever possible.

On the Netz NÖ side, approximately 22 people are currently working on the project. Since construction began, around 12,000 cubic meters of earth have been moved, approximately 3,500 cubic meters of concrete poured and around 280 metric tons of structural steel installed.

Next Steps

Over the coming months, APG will focus on completing the operations building, installing the transformers, setting up the 30-kV auxiliary power supply systems, and installing the equipment support structures and high-voltage equipment for the eleven planned switchgear panels.

 

About Austrian Power Grid (APG)

As an independent transmission system operator, Austrian Power Grid (APG) is in charge of ensuring the security of the electricity supply in Austria. With our high-performance and digital electricity infrastructure and the use of state-of-the-art technologies, we integrate renewable energies and reduce the dependency on electricity imports, we are the platform for the electricity market, and we provide access to reasonably priced electricity and thus create the basis for Austria as supply-secure and future-oriented industrial and business location and place to live. The APG grid totals a length of about 3,500 km and is operated, maintained, and continuously adapted to the increasing challenges of the electrification of businesses, industry, and society by a team of approximately 1,000 specialists. 67 substations are distributed all over Austria, and the majority are operated remotely from the control center in Vienna. Thanks to our committed employees, Austria had a security of supply of 99.99 percent also in 2025 and thus ranks among the top countries worldwide. Our investments of 680 million euros in 2026 (2025: 595 million euros, 2024: 440 million euros, 2023: 490 million euros) are a motor for the Austrian economy and a crucial factor for achieving Austria’s energy targets. Overall, APG will invest around 9 billion euros in grid expansion and modernization measures by 2035.


About Netz Niederösterreich: grid expansion by 2036

As a distribution system operator, Netz Niederösterreich must strengthen and expand the electricity grid at all voltage levels within a comparatively short period of time to facilitate the transition to a renewable energy future powered by wind, photovoltaics, energy storage, heat pumps and e-mobility for all our customers. This represents a major challenge:

  • Construction of approximately 71 new or replacement substations, including connection lines (92 substations are currently in operation).
  • Addition of approximately 700 transformer stations every year (compared with a long-term average of around 300).
  • Installation of approximately 1,000 km of medium- and low-voltage cables per year.

In the current financial year alone, Netz Niederösterreich is investing around EUR 590 million in infrastructure expansion to make the energy transition a reality.

Press contact

Foto_Stefan Walehrach.jpg

Stefan Walehrach

Wagramer Straße 19 (IZD-Tower)
1220 Wien

Phone +43 664 883 43 044 Email stefan.walehrach@apg.at
To the main navigation