To the content
Power line and wind turbines with setting sun in the background
Projects

Grid reinforcement east

The new 380 kV connection between Trumau (Lower Austria) and Zurndorf (Burgenland) will massively reinforce the extra-high voltage level in APG's transmission grid in eastern Austria. This reinforcement of the eastern grid is also important to ensure a secure supply of electricity throughout Austria. It plays a central role in the success of the secure energy transition and the decarbonization of the economy and society.

In planning

The new connection in the eastern region for the secure energy transition and increased integration of renewable energy

The climate targets set by Austria are leading to a massive expansion of wind power and photovoltaics in eastern Austria. In order to transport this energy to consumers throughout Austria, the transmission grid in eastern Lower Austria and northern Burgenland needs to be strengthened. This important grid expansion project is also anchored in the current integrated Austrian grid infrastructure plan (ÖNIP 2024). The connection between Trumau (Lower Austria) and Zurndorf (Burgenland) will significantly strengthen the 380 kV grid over a length of around 60 km: an important building block for the secure energy transition throughout Austria.
 The grid reinforcement east consists of the construction and conversion of overhead line infrastructure, most of which will run directly next to or in place of existing lines. The project also requires the construction and conversion of substations.</p

Project ticker

All current information about the project at a glance.

Project ticker

All current information about the project at a glance.

  • Update
  • Milestone
Update 29.05.2026

Initial information sessions for property owners in the project area

The Netzverstärkung Ost project, one of APG’s largest and most important current initiatives, was presented for the first time in May 2026 to affected property owners in the host communities in Lower Austria and Burgenland. On Monday, May 11, the first information session with property owners took place in the municipalities where the Netzverstärkung Ost project is located. The sessions began in the municipalities of Münchendorf and Moosbrunn in Lower Austria, followed by Himberg on May 12. In total, over 30 sessions were subsequently scheduled in 14 municipalities.

During these sessions, the project team explained the project, addressed the individual situations of the property owners, and answered specific questions. The focus was on open dialogue and active exchange on an equal footing. In Burgenland, Netz BURGENLAND is a project partner and was present at the information events in Parndorf and Neusiedl. The next step in public relations will take place in September 2026 with twelve public information fairs in the region.

The Netzverstärkung Ost project is part of the ÖNIP. The goal is to increase the east-west transmission capacities of the grid in order to make electricity generated from renewable energy sources in eastern Austria available throughout the country and to strengthen long-term supply security. The project involves the dismantling and construction of new overhead lines as well as the construction and expansion of substations, for example in Parndorf. In total, the construction of approximately 75 km is offset by the dismantling of approximately 70 km. In addition, a higher-capacity carbon cable will be installed on 16 km of the existing line.

Update 17.11.2025

Start of subsoil investigations

Austrian Power Grid (APG) starts on-site ground investigations in November as part of the Grid Reinforcement East project. The background to this is the planned construction and expansion of the 380 kV transmission grid in Lower Austria and Burgenland. The Grid Reinforcement East project comprises the conversion and new construction of a 380 kV overhead line in eastern Lower Austria and northern Burgenland, between Trumau (Lower Austria) and Zurndorf (Burgenland). A new high-performance connection is being planned over a length of just over 60 kilometers. The construction, expansion and conversion of local substations is also planned.In Burgenland, the project will be carried out in cooperation with Netz Burgenland and adjustments will be made to the 110 kV distribution grid. The new 380 kV line, most of which will run alongside or instead of existing lines, will increase the reliability of the region's electricity supply.

In order to be able to plan the project in detail, APG employees and experts commissioned by APG will be carrying out ground investigations on properties in the affected municipalities - in the districts of Baden, Mödling, Bruck an der Leitha and Neusiedl am See - over the coming months. The sole purpose of this work is to explore the conditions for an optimal route. The exploration campaign consisting of 22 core drillings and 40 excavator trenches with dynamic probing will start in November and is expected to last until the end of February 2026. The affected municipalities and property owners have already been personally informed about the work. Further information can be found at: Start of subsoil explorations for grid reinforcement east - Austria needs electricity

Milestone 10.04.2025

APG starts preparatory work for "Grid Reinforcement East"

Information on the planned grid expansion in Lower Austria and Burgenland

The Grid Reinforcement East project comprises the conversion and new construction of a 380 kV overhead line in eastern Lower Austria and northern Burgenland, between Trumau (Lower Austria) and Zurndorf (Burgenland). A new high-performance connection is planned over a length of around 60 kilometers. In addition, the expansion and conversion of local substations is planned. In Burgenland, the project will be carried out in cooperation with Netz Burgenland and adjustments will be made to the 110 kV distribution grid.

To the press release: www.apg.at/news-presse/apg-startet-vorarbeiten-zur-netzverstaerkung-ost/

appr. 75 km

Planned route between Trumau (Lower Austria) and Zurndorf (Burgenland)

380-kV

voltage level Electrification of the economy and industry in Lower Austria and Burgenland.

99%

security of supply in the household, industrial and commercial sectors

Renewable energy

flexibility option The new line enables the transport of surplus wind energy and electricity from photovoltaic systems in Burgenland and Lower Austria.

Construction phase from 2030

Commissioning: scheduled for the mid-2030s

Contact person

Portrait of Stefan Pölzlbauer

Stefan Pölzlbauer

Project lead

Wagramer Straße 19 (IZD Tower)
1220 Wien

Phone +436648286544 Email stefan.poelzlbauer@apg.at
WG_2.png

Wolfgang Gröger

Project communication

Wagramer Straße 19 (IZD-Tower)
1220 Wien

Phone +4366488342824 Email wolfgang.groeger@apg.at
To the main navigation