Salzburg line
The Salzburg line ensures energy security for Salzburg and the rest of Austria. The line is also crucial to reaching Austria’s climate targets, which makes it one of the most important infrastructure projects underway today.
Security of supply and sustainable integration of renewable energy.
With the goal of improving security of supply to the city of Salzburg, the first 46-km long section of the Salzburg line extending from the St. Peter node to the newly built Salzburg substation near Elixhausen was completed ahead of schedule and commissioned in January 2011.
With the second section being completed, the gap on the western side of the “ring” is now closed. Austria’s high-performance, extra-high voltage grid is characterised by its ring structure, which allows power to flow to customers from either direction. The 380-kV ring is the backbone of Austria’s electricity supply, and the new section of the Salzburg line will close the gap in the ring in western Austria. The 380-kV Salzburg line will replace the existing 220-kV line from the node at St. Peter am Hart (Upper Austria) to the Tauern bei Kaprun node (Salzburg).
Project ticker
All current information about the project at a glance.
Project ticker
All current information about the project at a glance.
- Update
- Milestone
Disassembly complete
With the successful completion of the dismantling work, the Salzburg Line project — one of Austria’s most significant electricity infrastructure projects — is finished.
Salzburg line in full operation
The Salzburg line is in full operation.
Step-by-step commissioning
The entire line system is to be considered permanently energized. The line will be energized step by step and the voltage of Salzburg Line 1 (UW St. Peter/OÖ to UW Salzburg), which has been in place since 2011, will be increased from 220 kV to 380 kV.
The dismantling of old 220 kV lines has already begun.
Construction progress
448 out of 449 pylons have been piled, construction lots 1 to 5 are structurally complete, remaining work will continue until commissioning in 2025.
Construction progress
Work to complete the Salzburg line is running at full speed. Currently, around 442 of 449 pylons have already been set.
128 km
approx. €1 bill.
449
678
6
36
6.7 km
38 km
Project Roadmap
Disassembly complete
678 old utility poles (spanning a distance of 193 km) were removed.
09. 04. 2025: Full operation of the Salzburg line
The Salzburg line is in full operation.
Demontagen
As soon as the new 380 kV Salzburg line is in operation, the dismantling of existing 220 kV and 110 kV lines will begin. The dismantling work is part of the Salzburg line project and part of the EIA approval process.
Administrative Court confirms approval for 380 kV line
The Administrative Court (VwGH) made the final decision on the project and confirmed the decision of the Salzburg state government dated 14.12.2015 in the version of the BVwG decision of 26.2.2019 in all points with its positive ruling of 15.10.2020.
Baustart
Start of construction of the Salzburg line.
Confirmation of EIA decision
Federal Administrative Court confirms positive EIA decision
EIA decision
Positive EIA decision 1st instance
Submission of project documents
Submission of the project documents to the EIA authorities
APG is investing in a sustainable and secure energy future in your region. For the economy and society as a whole.
Downloads
Dismantling
The dismantling was part of the Salzburg line project and had been approved as part of the EIA. In total, there will be 65 line kilometers and 229 pylons less than before Commissioning of Salzburg line in Salzburg due to the dismantling of old 220 kV lines and the fact that in certain sections the 110 kV lines of Salzburg Netz GmbH used the same pylons or underground cables. The easements of APG registered in the land registers on the dismantled line sections will be cancelled after the dismantling.
Contact person
Fritz Wöber
Project communication