To the content
Aerial photograph of the Salzburg pipeline under construction
Projects

Salzburg line

The Salzburg line ensures energy security for Salzburg and the rest of Austria. The line is also crucial to reaching Austria’s climate targets, which makes it one of the most important infrastructure projects underway today.

Completed

Security of supply and sustainable integration of renewable energy.

With the goal of improving security of supply to the city of Salzburg, the first 46-km long section of the Salzburg line extending from the St. Peter node to the newly built Salzburg substation near Elixhausen was completed ahead of schedule and commissioned in January 2011. 

With the second section being completed, the gap on the western side of the “ring” is now closed. Austria’s high-performance, extra-high voltage grid is characterised by its ring structure, which allows power to flow to customers from either direction. The 380-kV ring is the backbone of Austria’s electricity supply, and the new section of the Salzburg line will close the gap in the ring in western Austria. The 380-kV Salzburg line will replace the existing 220-kV line from the node at St. Peter am Hart (Upper Austria) to the Tauern bei Kaprun node (Salzburg). 

Project ticker

All current information about the project at a glance.

Project ticker

All current information about the project at a glance.

  • Update
  • Milestone
Update 28.10.2026
Bitte auf EN: Ein gelb-roter Hubschrauber im Flug, mittels Seil transportiert er einen Teil eines Strommastes ab.

Disassembly complete

With the successful completion of the dismantling work, the Salzburg Line project — one of Austria’s most significant electricity infrastructure projects — is finished.

Milestone 09.04.2025
An electricity pylon on the Salzburg line

Salzburg line in full operation

The Salzburg line is in full operation.

Update 21.02.2025

Step-by-step commissioning

The entire line system is to be considered permanently energized. The line will be energized step by step and the voltage of Salzburg Line 1 (UW St. Peter/OÖ to UW Salzburg), which has been in place since 2011, will be increased from 220 kV to 380 kV.

The dismantling of old 220 kV lines has already begun.

Update 05.09.2024

Construction progress

448 out of 449 pylons have been piled, construction lots 1 to 5 are structurally complete, remaining work will continue until commissioning in 2025.

Update 28.02.2024
DJI_0358-11.jpg

Construction progress

Work to complete the Salzburg line is running at full speed. Currently, around 442 of 449 pylons have already been set.

128 km

of new lines 114 km of 380-kV lines and 14 km of 220-kV lines

approx. €1 bill.

total investment volume

449

new electricity pylons 380-kV pylons: 404 220-kV pylons: 45

678

pylons dismantled enabling dismantling of 193 km of 220/110-kV lines

6

substations 2 newly built and 4 converted/adapted

36

municipalities

6.7 km

of 110-kV cabling

38 km

of 110-kV double circuit lines

APG is investing in a sustainable and secure energy future in your region. For the economy and society as a whole.

Salzburg Leitung; Pass Lueg
Salzburg Leitung; Pass Lueg


Dismantling

The dismantling was part of the Salzburg line project and had been approved as part of the EIA. In total, there will be 65 line kilometers and 229 pylons less than before Commissioning of Salzburg line in Salzburg due to the dismantling of old 220 kV lines and the fact that in certain sections the 110 kV lines of Salzburg Netz GmbH used the same pylons or underground cables. The easements of APG registered in the land registers on the dismantled line sections will be cancelled after the dismantling.
 


Contact person

fritz_woeber.jpg

Fritz Wöber

Project communication

Wagramer Straße 19 (IZD-Tower)
1220 Wien

Phone +436648286656 Email fritz.woeber@apg.at
To the main navigation