Energy security for central Upper Austria
APG is working together with project partners Netz OÖ and Linz Netz on a project called “Energy security for central Upper Austria”. The project is aimed at upgrading the existing power grid to meet the challenges of the future.
Working to ensure energy security in your region
“Energy security for central Upper Austria” is an APG project designed to guarantee a sustainable supply of electricity for the region and to support energy transition, including the electrification of the economy, industry and society.
Project ticker
All current information about the project at a glance.
Project ticker
All current information about the project at a glance.
- Update
- Milestone
Construction phase 1
Particularly exciting in the partner project "Secure power supply central Upper Austria" by APG, Netz OÖ & Linz Netz: Construction phase 1 - the existing & single cable section will be extended by three cable systems by 2026. Watch the video to find out how the construction phase will be implemented & and what challenges will be overcome to ensure a secure power supply! ????
APG in the high-voltage podcast of Netz OÖ!
APG project manager Mario Golger talks to Wolfgang Denk (press spokesman for Netz Oberösterreich GmbH?) in the latest podcast episode about the progress of the "Secure power supply in the central Upper Austrian region" project.
The implementation of the partner project between APG, Netz OÖ and Linz Netz will ensure a sustainable power supply in the region and enable the energy transition and the electrification of the economy, industry and society.
Listen in now: https://bit.ly/3UsHsdk
First of three transformers arrives at Hütte Süd substation
On Tuesday, March 25, the first of this year's three 220/110 kV transformers was delivered to the Hütte Süd substation. With a transport weight of 272 tons and an output of 300 megavolt amperes (MVA), this electricity giant is making a key contribution to ensuring a secure supply and a strong economic and living location in Upper Austria.
The transport of the giant transformer was a logistical masterpiece: the electricity giant was transported from the Siemens plant in Weiz by train on an approximately 14-metre-long through-loading carrier to the heavy-duty port in Linz. There it was reloaded onto a special 14-axle road transporter consisting of several heavy-duty modules. The special feature: the heavy-duty transporter is precisely operated and controlled by remote control. Once it arrived at the substation, the 272 tons were then placed on cross rails in front of the transformer foundation, the transformer's new workplace, by means of a lifting frame and pulled onto the foundation the following day with millimetre precision. Once fully upgraded, the transformer will weigh 445 tons. In April and June of this year, two more 220/110 kV transformers will be delivered to the Hütte Süd substation. The 900 MVA output of the three transformers will then be roughly equivalent to the output of three large Danube power plants. This will significantly increase the feed-in capacity for climate-friendly electricity and enable a secure energy transition in the region.
Click here for the press release.
Information consultation day in Linz
In the course of the ongoing construction work for the "Secure Power Supply Central Upper Austria" project, another information consultation day was held for citizens on March 11. After two successful information events were held in Kronstorf and St. Florian in September 2024, this time it was Linz's turn. At the Pichling sports park, we provided information primarily about the current work in construction phase 1.
Between 3 and 6 p.m., interested citizens had the opportunity to make personal contact with a team of around 12 experts, consisting of APG employees and the project partners Netz Oberösterreich and Linz Netz. They were able to obtain comprehensive information about the ongoing work in their area and about the project as a whole.
In numerous personal discussions, citizens were able to address their individual concerns and questions directly to the team of experts.</p
The first mast is in place
The erection of the first electricity pylon marks an important technical and symbolic milestone in the "Secure Power Supply Central Upper Austria" project.
This pylon in the area of the market town of St. Florian is part of the quadruple line that will run two 220 kV systems (APG) and two 110 kV systems (Netz OÖ) from the Ernsthofen substation to the Pichling substation.
The pylon is the first of 138 pylons that will be erected as part of the overall project. In construction phase 2 (2024-2026), which is currently under construction, work on the other pylon locations, such as foundation work or pylon pre-assembly, is already in full swing.</p
Official ground-breaking ceremony for a secure power supply in the central Upper Austrian region has taken place
Today saw the official ground-breaking ceremony and thus the starting signal for the major energy industry project "Secure Power Supply Central Upper Austria" by APG, Netz OÖ and Linz Netz. The project is a prerequisite for the decarbonization of industry in the region (e.g. electricity-based steel production) and thus the basis for a significant CO2 reduction and the success of the secure energy transition in the region and throughout Austria.
To mark the start of the project, the project applicants APG, Netz OÖ and Linz Netz, represented by Gerhard Christiner, CEO of APG, Marcus Karger, Commercial Director of APG, as well as the managing directors of the project partners Netz OÖ Manfred Hofer and Michael Haselauer, and Linz Netz Johannes Zimmerberger, invited guests to the ground-breaking ceremony at the Pichling substation. Also present were Stefan Kaineder, Upper Austria's State Councillor for the Environment and Climate, Christian Mader, Member of Parliament (standing in for Markus Achleitner, State Councillor for Economic Affairs and Energy), Gerald Mayer, CFO of voestalpine AG and Jürgen Schneider, Head of the Climate and Energy Section at BMK.
<pInformation days on project implementation
On the occasion of the start of construction this summer for the "Secure Power Supply Central Upper Austria" project, two information consultation days were held in the municipalities of Kronstorf and St. Florian on September 10 and 11.
The dedicated APG project team and the project partners Netz Oberösterreich and Linz Netz were on site from 4 p.m. to 7 p.m. to provide interested citizens with comprehensive information. Around 80 visitors took the opportunity to find out about the project in general, the route of the line, the measures in the individual construction phases and substations, the technology used and various accompanying measures.
In numerous personal discussions, individual questions were answered in detail. We were very pleased about the lively exchange with the population from the project region and greatly appreciate the great interest and constructive discussions.</p
Start of construction work
After the Federal Administrative Court (BVwG) confirmed the positive EIA decision of the province of Upper Austria in the second instance at the end of June 2024, preparatory construction measures for the "Secure Electricity Supply Central Upper Austria" project were started and implemented immediately, meaning that the actual implementation of the project can now begin.
The construction work for the project will start with the first two of a total of four line construction sections and at the two substations Kronstorf and Pichling. This will be followed by expansion and conversion work at six further substations as part of the project. The supply ring will be commissioned in stages from 2026 to 2030.
More information and details in the press release.
BVwG confirms environmental compatibility of the project
It is a milestone for the "Secure Power Supply Central Upper Austria" project and thus for the energy transition in Austria. Following the positive EIA decisions by the federal states of Upper Austria and Lower Austria in March 2023, the Federal Administrative Court (BVwG) has now also confirmed the EIA approval for the Upper Austrian part of the project in the second instance on June 24.
Next steps
However, with this confirmation of the positive EIA decision by the BVwG, not only has the environmental compatibility of the project been confirmed once again, but the approval can also be consumed in full. There is also no longer any suspensive effect, which means that the necessary steps can now begin before the actual start of construction. These include the implementation of ecological requirements (e.g. amphibian fences), construction site equipment, site clearance and other preparatory work. As soon as these have been completed, project implementation can begin.
Click here for the press release: Milestone reached for energy transition in Austria - Austria needs electricity (apg.at)
BVwG hearing
Almost exactly one year ago (in March 2023), the responsible environmental impact assessment authorities, the province of Upper Austria and the province of Lower Austria, confirmed the environmental compatibility of the joint project of the three grid operators. Following the lodging of three appeals (one of which has since been rejected by the Supreme Court) against the positive EIA decision of the province of Upper Austria, the second-instance hearing regarding the two pending appeals was held before the Federal Administrative Court in Vienna on 4/5 and 7 March 2024 (the approval for the Lower Austrian part of the project was already legally binding in the first instance).
The three-day hearing was very orderly and structured. Topics included electrical engineering and the energy industry, nature and landscape conservation, forestry and human medicine.</p
Hut South
On Tuesday, March 21, 2023, the ground-breaking ceremony took place for the expansion of the Hütte Süd substation of Austrian Power Grid AG (APG), which is also part of the joint Central Upper Austria project cluster. As a new 220/110 kV node, the future expanded substation is central to the decarbonization of Upper Austria as an industrial and business location and thus enables the success of the secure energy transition in the region and throughout Austria.
The Hütte Süd substation is also an essential grid-related part of the partner project "Secure Power Supply Central Upper Austria" of APG, Netz OÖ and Linz Netz, with which the central region will be made fit for the future, especially with regard to capacity requirements. However, the expansion of the substation is not a legal part of the EIA process.</p
Approval granted with positive EIA decision from the state
The province of Upper Austria, as the EIA authority conducting the procedure, confirms the environmental compatibility of the joint project "Secure Power Supply Central Upper Austria" of Austrian Power Grid (APG), Netz Oberösterreich GmbH (Netz OÖ) and LINZ NETZ GmbH (LINZ NETZ).
From 29 November to 2 December 2022, the oral hearing was held by the EIA authority (Province of Upper Austria) at the Design Center in Linz. Only three months later (09.03.2023), the positive EIA decision was issued by the authority. This decision is the result of the professional handling of the EIA procedure by the EIA authority. This decision is an important milestone in the realization of one of the country's most important infrastructure projects. An important contribution to the secure supply of electricity, the success of the energy transition and the electrification of the economy, industry and society in the region and for Austria as a whole.
The decision shows that there will be no negative effects in terms of nature conservation or human medicine. The authority therefore concludes that the "Secure Power Supply Central Upper Austria" project is environmentally compatible and permissible in light of the expert reports and the results of the EIA procedure carried out.
Read more in the press release.</p
2024 - 2030
approx. 42 km
Increasing electrification
approx. 800 Mio €
220-kV
Strong
Project Roadmap
Construction phase 4
Open-circuit line (city connection) between the Wegscheid substation and the Linz Süd district heating power plant.
Construction phase 3
Open-circuit line from the Kronstorf substation in the direction of Asten to the Wegscheid substation
.Construction phase 2
Open-circuit line from the Ernsthofen substation in the direction of Asten to the Linz Süd district heating power plant
.Construction section 1
Extension of the existing cable section between the Pichling transformer station and the Traunauen
.Baustart
Baustart
BVwG finding
Positive EIA decision and environmental compatibility confirmed by the Federal Administrative Court (BVwG) in the second instance
BVwG hearing
Oral hearing in the second instance at the BVwG in Vienna
EIA decision
Positive EIA decisions have been issued by the Upper Austrian and Lower Austrian provincial governments.</p
EIA negotiation
The oral EIA hearing took place at the Design Center in Linz.
<pSubmission of EIA
Submission of the project documents in accordance with the Environmental Impact Assessment Act (UVP-G 2000) to the competent authorities of the provinces of Upper and Lower Austria.
Planning
Planning and preparation of the project documents
.Project information
At present, all of central Upper Austria is supplied with electricity via a 110-kV power grid only. The current 110-kV grid is not equipped to meet the challenges of the future or to support the rapid pace of development underway throughout the central region of Upper Austria. This means that the region’s existing power infrastructure will reach the limits of its capacity in just a few years.
Electricity consumption is set to increase significantly in central Upper Austria in the coming years. The reason is dynamic growth of the Enns-Steyr power region/economic area as well as advancing electrification and the conversion of industrial processes that goes along with this (e.g. voestalpine’s transition to electricity-based steel production). Rising consumer numbers are also a factor. According to the population forecast of the state of Upper Austria, there is a projected growth to approximately 332,500 inhabitants by 2045 in Linz, Wels and Steyr alone.
Austrian Power Grid (APG), Netz Oberösterreich GmbH (Netz OÖ) and LINZ NETZ GmbH (LINZ NETZ) are working together to transform the power grid – to make sure you continue to be supplied with electricity whenever you need it. A 220-kV supply ring will be built to replace the existing 110-kV lines.
Secure power supply central region of Upper Austria
Frequently asked questions - FAQ
Once completed, the planned 220-kV supply ring will link APG’s substations in Ernsthofen, Pichling, Hütte Süd, Wegscheid and Kronstorf. The system operator’s concept includes the following components:
- replace existing transmission lines;
- voltage conversion (from 110 kV to 220 kV) of the line sections already ready for 220 kV;
- expansion and conversion work at a total of eight substations; and
- work to dismantle the 110-kV lines no longer needed.
To keep the impact on people and the environment as low as possible, the new transmission lines will be installed along existing line routes of APG, Netz OÖ and LINZ NETZ.
Affording equal treatment to all property owners is of the utmost priority for APG and its project partners, Netz OÖ and Linz Netz.
Our power lines can impact properties in one of three ways:
- when an electricity pylon is erected on the property;
- when the property is traversed by overhead transmission lines (whereby only the land within the easement area through which the lines run is impacted); and
- when forest areas are cleared.
The compensation to be paid for appropriated land (including agricultural land and forested areas) is stipulated in a framework agreement drafted in cooperation with the Upper Austria Chamber of Agriculture.
The framework agreement governs the calculation of the compensation amount stipulated in the private-law easement agreement to be entered into by mutual agreement with all property owners. It also stipulates a number of general conditions relevant to the construction and operation of transmission line systems.
The framework agreement applies equally to all land used for agricultural or forestry purposes, thus ensuring a uniform and equitable approach toward all.
- The Environmental Impact Assessment (EIA) comprises Austria’s strictest review and approval process. The EIA process is designed to ensure that the entire project is presented in a transparent and detailed manner and that stakeholders (e.g. property owners, local communities, etc.) and other parties involved in the process are able to inspect and comment on the project documents.
- Prior to submitting the EIA, an environmental impact statement (EIS) is prepared. In addition to a precise description of the project, the EIS comprises 20 expert reports subject to review and is the main component of the subsequent environmental impact assessment process. The EIS is submitted to the EIA authorities responsible for the assessment procedure (the governments of the states of Upper and Lower Austria).
- That documentation is taken as the basis for the review and assessment of the project’s potential impact on material assets specific to the region, such as humans and wildlife, soil, water and the landscape. Following comprehensive review by the EIA authorities, an environmental impact assessment report is issued.
- After the EIA report has been issued, an oral EIA hearing is held, which is scheduled by the EIA authority.
- Finally, the EIA authority issues a decision, which ideally becomes legally binding after an objection period.
The present network development plan will serve to establish a secure, efficient and high-performance supply of power to support the future development of central Upper Austria. It will improve the integration of renewable energy sources to make clean energy available throughout Austria.
The integration of green electricity is a crucial part of the network development plan, as it will be necessary to electrify industrial processes if the energy transition is to succeed. voestalpine, for instance, will only be able to switch to new, carbon-friendly technologies – i.e. electricity-based steel production – if it has access to a high-performance power grid.
The investment volume amounts to around 800 million euros.
The amount stated is the investment sum of the three project partners, which is exposed to price changes on the global market, particularly due to the long implementation period until 2030.
The “Energy security for central Upper Austria” project will take place in stages from 2026 to 2030.
Contact person

Mario Golger
Project lead

Stefan Walehrach
Project communication

Projekt Postfach ZROÖ
Project folder Energy security for central Upper Austria (German only)
Downloads
-
Übersicht Trasse und Bauabschnitte
PDF – 0.075 MB
-
Projektfolder
PDF – 1.457 MB
-
Bauabschnitt 1
PDF – 1.197 MB
-
Bauabschnitt 2
PDF – 0.553 MB
-
Bauabschnitt 3
PDF – 0.548 MB
-
Bauabschnitt 4
PDF – 0.542 MB
-
Gemeindefactsheet Linz
PDF – 1.229 MB
-
Gemeindefactsheet St. Florian
PDF – 1.522 MB
-
Gemeindefactsheet Ernsthofen
PDF – 1.44 MB
-
Gemeindefactsheet Kronstorf
PDF – 1.446 MB
-
Gemeindefactsheet Hargelsberg
PDF – 1.202 MB
-
Gemeindefactsheet Asten
PDF – 1.374 MB
-
Gemeindefactsheet Enns
PDF – 1.358 MB