To the content
Aerial photograph of the Salzburg pipeline under construction
Projects

Salzburg line

The Salzburg line ensures energy security for Salzburg and the rest of Austria. The line is also crucial to reaching Austria’s climate targets, which makes it one of the most important infrastructure projects underway today.

Completed

Security of supply and sustainable integration of renewable energy.

With the goal of improving security of supply to the city of Salzburg, the first 46-km long section of the Salzburg line extending from the St. Peter node to the newly built Salzburg substation near Elixhausen was completed ahead of schedule and commissioned in January 2011. 

With the second section being completed, the gap on the western side of the “ring” is now closed. Austria’s high-performance, extra-high voltage grid is characterised by its ring structure, which allows power to flow to customers from either direction. The 380-kV ring is the backbone of Austria’s electricity supply, and the new section of the Salzburg line will close the gap in the ring in western Austria. The 380-kV Salzburg line will replace the existing 220-kV line from the node at St. Peter am Hart (Upper Austria) to the Tauern bei Kaprun node (Salzburg). 

Project ticker

All current information about the project at a glance.

Project ticker

All current information about the project at a glance.

09.04.2025
An electricity pylon on the Salzburg line

Salzburg line in full operation

21.02.2025

Step-by-step commissioning

The entire line system is to be considered permanently energised. The line will be energised step by step and the voltage of Salzburg Line 1 (UW St. Peter/OÖ to UW Salzburg), which has been in place since 2011, will be increased from 220 kV to 380 kV. The dismantling of old 220 kV lines has already begun. 

28.02.2024

Construction progress

The work to complete the Salzburg line is running at full speed. Currently, around 442 of 449 pylons have already been set.

05.09.2024

Construction progress

448 of 449 pylons are in place, construction lots 1 to 5 structurally completed, remaining work will continue until commissioning in 2025 

128 km

of new lines 114 km of 380-kV lines and 14 km of 220-kV lines

approx. €1 bill.

total investment volume

449

new electricity pylons 380-kV pylons: 404 220-kV pylons: 45

678

pylons dismantled enabling dismantling of 193 km of 220/110-kV lines

6

substations 2 newly built and 4 converted/adapted

36

municipalities

6.7 km

of 110-kV cabling

38 km

of 110-kV double circuit lines

APG is investing in a sustainable and secure energy future in your region. For the economy and society as a whole.

Salzburg Leitung; Pass Lueg
Salzburg Leitung; Pass Lueg


Dismantling

As soon as the new 380 kV Salzburg line is in operation (scheduled for 2025), the dismantling of the existing 220 kV and 110 kV lines will start. The dismantling is part of the Salzburg line project and has been approved as part of the EIA. In total, there will be 65 line kilometers and 229 pylons less than today in Salzburg due the dismantling of old 220 kV lines and the fact that in certain sections the 110 kV lines of Salzburg Netz GmbH will use the same pylons or underground cables. The easements of APG registered in the land registers on the dismantled line sections will be cancelled after the dismantling.

The dismantling work will be carried out in seven sections. The maps and the contact persons responsible for the respective sections can be found in the relevant download area and in the list below.

Specifically, APG and its project partner Salzburg Netz will dismantle the following lines

  • 220 kV line substation Salzburg – grid node Tauern, starting from the grid node Tauern in the municipality of Kaprun to pylon no. 322 in the municipality of Seekirchen am Wallersee (APG)
  • 220 kV line grid node Tauern – substation Weißenbach, starting from the grid node Tauern in the municipality of Kaprun to pylon no. 165 in the municipality of Wagrain (APG)
  • 110 kV line substation Kaprun - substation Schwarzach, starting from the substation Kaprun in the municipality of Kaprun to pylon no. 77 in the municipality of Taxenbach (APG)
  • 110 kV line substation Pongau - substation Golling, starting from the substation Pongau (municipality of St. Johann im Pongau) to pylon no. 70 in the municipality of Werfen (Salzburg Netz)

Due to the necessary construction site clearances for the erection of the 380 kV Salzburg line, the following dismantling works have already been carried out:

  • 110 kV line power plant Arthurwerk - substation Annaberg/Strobl, starting from the power plant Arthurwerk in the municipality of St. Johann im Pongau to pylon no. 8 in the municipality of St. Johann im Pongau.
  • 110 kV line substation Pongau - substation Reitdorf, starting from the substation Pongau in the municipality of St. Johann im Pongau to the east of the river Salzach
  • 110 kV line power plant Dießbach (substation Pinzgau) - substation Pongau between Einöd (pylon no. 117) and substation Pongau
  • 110 kV line substation Pinzgau - substation Pongau, section of pylons no. 8 to 11 (approx. 1.2 km).
  • 110 kV line substation Pongau - substation Golling, section of pylons no. 71 to 105 (Pass Lueg)

Contact person

APG, Herbert Auer

Herbert Auer

Project lead

Wagramer Straße 19 (IZD-Tower)
1220 Wien

Email salzburgleitung@apg.at
fritz_woeber.jpg

Fritz Wöber

Project communication

Wagramer Straße 19 (IZD-Tower)
1220 Wien

Phone +436648286656 Email fritz.woeber@apg.at
placeholder_division.png

Projekt Info-Hotline

Project office Salzburg line

Hauptstraße 73
5600 Sankt Johann im Pongau

Phone +43 800 311 680
Michael-Hatzer-20220526_210728-neu.jpg

Michael Hatzer

Dismantling Section 3

Wagramer Straße 19 (IZD-Tower)
1220 Wien

Phone +43 664 415 5598 Email michael.hatzer@apg.at
martin-auer.jpg

Martin Auer

Dismantling Section 3

Wagramer Straße 19 (IZD Tower)
1220 Wien

Phone +43 664 88782809 Email martin.auer@apg.at
IMG_E0726.JPG

Christoph Müllauer

Dismantling Section 2

Wagramer Straße 19 (IZD-Tower)
1220 Wien

Phone +43 664 828 5519 Email christoph.muellauer@apg.at
To the main navigation