Weinviertel line

Replacement of the Weinviertel line, which is over 70 years old, will ensure that APG will have a sustainable grid connection both now and in the future and that your region and all of Lower Austria will have a secure supply of electricity.

In progress

The new line is necessary as a basis for the continued integration of wind and solar energy and its distribution throughout the region and across Austria. 

Upon completion in the summer of 2022, the Weinviertel line will make a key contribution to the success of energy transition and to the electrification of the economy, industry and society. 

APG_drohne8.jpg
APG_drohne7.jpg

62 km

of lines 48 km of 380-kV lines and 14 km of 220-kV lines

€132m

in added value for Austria €31m of which for Lower Austria

202

electricity pylons or 53 fewer pylons (15 km shorter) than in the existing system

2,100

jobs created 600 of which in Lower Austria

approx. €200m

total investment volume

Summer 2022

Commissioning

Project information

Designed to feed the ever-increasing quantities of wind power generated in the Weinviertel region into APG’s trans-regional power grid, the Weinviertel line project represents one of APG’s biggest and most important projects in support of Austria. APG is investing around 200 million euros into the Lower Austrian economy in connection with the project. 

The new line will improve energy security and strengthen stability of supply in your region and in all of Lower Austria. Integrating wind and solar energy from the Weinviertel region into the grid will also make a key contribution to reaching the targets set in Lower Austria’s 2030 Climate and Energy Plan as well as the Austrian climate and energy targets. 

Due to its many years in operation, the existing system needed to be completely overhauled. The route corridor, for example, was no longer ideal for meeting future demand. It was therefore necessary to develop a new corridor that would account for the changing geographical distribution of the power supply. In the future, APG’s new 380-kV Weinviertel line will run from Seyring to the Zaya substation, which will be rebuilt in connection with the project. From the Zaya substation, new connections were made to the 110-kV grid in Lower Austria as well as to a 220-kV line extending to the Czech border. Both the Weinviertel line and the Zaya substation went online in the summer of 2022. 


Project ticker

All current information about the project at a glance.

Project ticker

All current information about the project at a glance.

  • Update
  • Milestone
Update 15.12.2022

Dismantling work on the existing pipeline is going according to plan

Immediately after the successful commissioning of the new Weinviertel line in summer 2022, the dismantling work of the existing line has also begun. Part of the pylons will be removed by helicopter and transported away. After a short period of bad weather, the pylon locations in the Weinviertel region, which are only accessible via the ground, have already been dismantled by helicopter.

Thanks to optimised planning and implementation, the project is well on schedule. "The high level of motivation during the elaborate preparations by the project team of the Weinviertel line was matched in no way by the partners carrying out the work, with a remarkable dismantling rate of around 4 pylons per hour (3 approaches per pylon)," praises Andreas Pischel, project manager of the Weinviertel line.

In the meantime, 228 of 255 pylons have already been successfully dismantled. The remaining 27 pylons will be removed at the beginning of next year. In addition to the removal of the pylons, the foundations must also be dismantled. Here, the work is also proceeding according to plan in coordination with the ecological building inspectorates and, of course, the landowners.

Milestone 12.09.2022

Official inauguration and commissioning of the Weinviertel line

The Weinviertel line, and with it the substation at Neusiedl an der Zaya, commenced full operation right on schedule. On 12 September 2022, the informational event for the commissioning was held in Neusiedl an der Zaya. At the invitation of APG, the event was attended by Governor Johanna Mikl-Leitner, EVN board members Stefan Szyskowitz and Franz Mittermayer, Mayor Andreas Keller, APG Supervisory Board Chairman Peter F. Kollmann and APG CTO Gerhard Christiner.


Now that it’s been completed, the Weinviertel line is making a vital contribution to a secure supply of electricity in Lower Austria and in Austria as a whole. Going forward, the line will feed up to 3,000 MW of renewable energy from Lower Austria into APG’s trans-regional grid for use throughout all of Austria. A true milestone in the transition to new forms of energy! 

Update 19.08.2022

Commissioning

After a construction period of just three years, all work has now been completed. Both the Weinviertel line and the Zaya substation will go into operation in the summer of 2022. 


The Zaya substation fulfils an especially important function as additional grid support for Netz NÖ, the regional distribution system operator. The new feed-in station enables the wind and solar power generated in the Weinviertel region to be fed into APG’s trans-regional grid for use across all of Austria.


Project planning and implementation focused on protecting environmental and conservation interests relating to people and nature and on incorporating the existing infrastructure. The new route corridor no longer passes through the Bernhardsthaler Ebene nature reserve, and it also circumvents settled areas. 
 

Update 25.04.2022

Construction work enters the home stretch

Construction of the Weinviertel line and the Zaya substation is progressing in leaps and bounds. The line will be commissioned in less than one year. 


Erection of the pylons was successfully completed in all three construction sections. Good progress has also been made with the cable work, which is around 75% finished.


Work at the Zaya substation itself has also been going well. The transformers have been upgraded and the building systems are in place, meaning that all buildings, foundations and cable ducts are ready to go. The 380-kV and 220-kV GIS systems have been installed and subjected to high-voltage testing. At present, all plant systems are being tested.

Update 25.04.2022

All roads lead to the Zaya substation (transporting transformers)

The transformer is the heart of the substation. Transformers convert the incoming voltage coming from APG’s high-voltage network to a voltage suitable for the regional distribution system operators, and vice versa.


In mid-May 2021, the first transformer reached its new home at the Zaya substation. Weighing in at around 300 tonnes, this massive piece of equipment took several days to reach its destination – just like the later transformers arriving in June and September. The journey started at the Siemens factory in Weiz/Austria. The transformers then travelled by train to Hohenau an der March, where they were crane lifted onto a low loader special transport vehicle that transported them to the Zaya substation and placed them on their foundations.

Update 25.04.2022

A transformer named “Carlo”

In July 2021, an old tradition was brought back to life at the substation in Neusiedl an der Zaya – inaugurating a new transformer. The inauguration ceremony was performed by Karl Wilfing, the president of the Lower Austrian Parliament, in the presence of Gerhard Christiner, the Chief Technical Officer (CTO) of APG; Stefan Szyszkowitz and Franz Mittermayer, EVN board directors; mayor Andreas Keller; fire chief Roman Stur, OBI; along with the press. He christened the approximately 300-tonne heavy transformer “Carlo” as per its nickname.


In expressing his satisfaction with the project, President Wilfing said “Just as I am energised by the prospect of our country being on the right track, our new transformer, “Carlo”, will also provide energy to help the energy transition succeed and to ensure a secure and sustainable supply of electricity. That’s why I’m so pleased to sponsor this 300-tonne transformer named Carlo. Carlo is part of Lower Austria’s climate and energy roadmap, and is a good example of how important it is to move from setting goals to getting results.”

Frequently asked questions - FAQ

How will the new Weinviertel line be routed?

In the future, the new 380-kV Weinviertel line will run from Seyring to the Zaya substation, which will be rebuilt in connection with the project. At the Zaya substation, a new connection will be made to the 110-kV grid in Lower Austria and to a 220-kV connection extending to the border with the Czech Republic.

How was APG's Weinviertel line planned?

APG's new Weinviertel line to replace the existing 220-kV line must be subjected to an official approval procedure pursuant to the 2000 Environmental Impact Assessment Act (Umweltverträglichkeitsprüfungsgesetz 2000, UVP-G 2000). The Lower Austria state government is responsible for the approval process, since the planned line will be located exclusively in Lower Austrian territory.

APG must therefore show that the line meets the statutory requirements for the protection of people and nature upon submitting the project for official review. Experts in 24 fields carried out inspections on the site of the planned project for the purpose of drawing up the detailed project planning documents.

This necessitated accessing private property along the planned line in some cases. The Lower Austrian state authorities granted APG a preliminary works approval notice in April 2015 as the legal basis for conducting the inspections.

Taking the initially planned cooridor as the basis, the corridor was fine-tuned step-by-step over the following 14 months until the current route of APG's Weinviertel line was finalised. In planning the route, the following criteria were of particular importance to APG and its employees:

  • the involvement of communities, property owners and other local stakeholders in the planning process;
  • consideration of all environmental or conservation interests relating to people and nature; and
  • connections with the existing infrasturcture (Lower Austrian grid's 110-kV line, wind farms, etc.).

In addition, the many in-person discussions that APG project employees held with representatives of the communities along the route, the property owners affected and neighbouring parties were a crucial part of the overall planning process. This was the only way to come up with potential improvements to the proposed route plan and to discuss them with the parties involved at a local level. Many of the suggestions from the community and the property owners were incorporated into the plans and are now reflected in the probable route of APG's Weinviertel line replacement. 

How was the public informed about the project?

It is of great importance to Austrian Power Grid?AG (APG) that individual stakeholders be informed at an early stage during the entire duration of the “APG Weinviertel line replacement” project.

Of particular significance is involving the public in the route development process, providing comprehensive information on the individual project steps, ensuring open communication and working together constructively with members of the public and their political representatives.

The project team began initiating personal contact with the property owners at the same time the info letter was sent. To ensure that the process would be as simple as possible with direct contact and support during the entire duration of the project, the project area was divided into five sections, with each section being assigned to an APG employee as the direct contact person for the property owners. The contact information of the APG contact person responsible for each section was supplied to all property owners in the initial info letter.

One of the main requests received during the many discussions with property owners, neighbouring parties and community representatives during the planning phase related to optimising the placement of the pylons as well as the route. The discussions were successful in identifying potential improvements that could be taken into consideration in the route now defined.

At the end of the planning phase, all of the communities affected by APG’s Weinviertel line replacement were invited to a consultation day at which information was provided to all interested parties. Local residents were invited to attend the consultation day in their community through flyers circulated by bulk mail or ads in community newspapers, while property owners were sent individual letters.

In addition, a project folder containing information on each of the project phases was made available to interested parties. 

Is there compensation for use of land?

In principle, a plot of land can be claimed either by a mast site itself or by an overvoltage - in this case, only the conductor cables and the associated servitude area pass over the plot of land. How the claimed agricultural and forestry areas are compensated is regulated uniformly for all landowners in the APG guideline. Ensuring a uniform procedure and equal treatment of all landowners is a top priority for APG.

The guideline regulates the calculation of the amount of compensation for the easement agreements to be concluded with the landowners under private law and by mutual agreement. The guideline of APG ensures a uniform, appropriate and cooperative approach to land claims for the replacement construction of the APG wine district pipeline and is divided into 3 sub-areas:

  • agricultural land
  • forestry land
  • general

If the area claimed is an agriculturally used and dedicated plot of land, the compensation fee is determined on the basis of the guideline. The different market values in the project region are also taken into account.

If the area claimed is a forest that has to be felled in the course of the construction of the pipeline or during operation, the amount of the compensation payment is assessed by an expert on the basis of the guideline. The valuation is carried out according to recognized methods of forest value calculation.

APG also undertakes to compensate for the damage to land resulting from the construction of the pipeline in accordance with the "Compensation Guideline for the Utilization of Agricultural and Forestry Land" issued by the Lower Austrian Chamber of Agriculture.

What is an environmental impact assessment?

The Environmental Impact Assessment (EIA) is made in an integrated approval process. That means that once an application for approval of a project is submitted, the responsible EIA authority (the Lower Austrian state government) proceeds to apply all substantive laws relevant to the project in an integrated procedure. The EIA authority then decides on the eligibility of the project for approval. In making the decision, extremely strict criteria are applied regarding the impact on people and nature.

How is the work to dismantle the old line coming along?

Work to dismantle the existing line began in the summer of 2022. Some of the work will require the use of an auto crane or a helicopter, depending on local conditions. Thus the dismantling operation may lead to noise disturbances from time to time. The work to dismantle the old line will be completed by the spring of 2023.


After the line has been dismantled, APG will have the corresponding easements deleted from the respective property registers. This could take several months, however, depending on the land registry in question.

Contact person

Andreas Pischel.jpg

Andreas Pischel

Wagramer Straße 19 (IZD-Tower)
1220 Wien

Phone +43 664 88342835 Email andreas.pischel@apg.at
Foto_Stefan Walehrach.jpg

Stefan Walehrach

Wagramer Straße 19 (IZD-Tower)
1220 Wien

Phone +43 664 883 43 044 Email stefan.walehrach@apg.at
To the main navigation