Seiltausch Kaprun-Weissenbach

Altersbedingte Kapazitätseinschränkungen bei der Stromübertragung gehören der Geschichte an.

APG is investing in securing the supply of power for the greater Styria region and Salzburg: around 18.5?million euros was spent on upgrading the entire 220-kV cable system running between the substations in Tauern and Weißenbach. 

DSC_4823_1.jpg
Erneuerung 220-kV-Freileitung im Ennstal, Austrian Power Grid

Project information

Demands on the power grid have increased greatly in recent years, and demand will only continue to rise. That’s why it is absolutely vital to have secure, high-performance power lines in place that are capable of meeting the requirements of the future and maintaining Austria’s high level of energy security. APG willl invest 3.5 billion euros in upgrading the domestic electricity infrastructure by 2031.  

The APG line running between the substations in Weißenbach (Styria) and Tauern (Salzburg) was built and commissioned in 1949. After 70 years in operation, the line was showing its age in the form of restricted capacity to transmit electricity. APG has upgraded the cable line of the existing system to ensure a secure and sustainable supply of power to economically important regions and popular tourist destinations. 

Forecasts for the energy market attest to the growing significance of high-capacity power grids, especially in winter, as does the increasing electrification of the economy. Maintaining a high level of supply quality is indispensable for the tourist centres in and around the Enns Valley.

approx. €18.5m

euros Total investment volume

State-of-the-art technology

The new cable lines are equipped with a special coating to ensure full capacity during power transmission and to minimise corona noise in the interest of local residents in particular.

2

Two construction stages Weißenbach substation – Wagrain connection point Tauern substation – Wagrain connection point

125

km of lines (68.8 km in Salzburg and 56.3 km in Styria)

Cable exchange process 

Work to replace the cable system commenced in March 2021 and was completed in July 2021. The work was done in two sections: 

Section A: from the Weißenbach substation to the Wagrain connection point 

Section B: from the Wagrain connection point to the Tauern substation 

The new cable line was connected to the existing cable and pulled along the route corridor using a cable winch. The existing road networks in combination with temporary construction site roads were used in executing the work. Protective scaffolding was also put up at important intersections so that no roads had to be blocked while the work was ongoing.  

Given that the cable replacement was considered maintenance work, no environmental impact assessment was required prior to commencing work. 

A sustainable connection to support the energy transition

Austria has pledged to use energy generated from 100% renewable sources to meet its electricity needs by 2030. APG’s Kaprun–Weißenbach line – with its improved integration and ability to transport green electricity – is a key component in the success of the transition to renewables and the electrification of the economy, industry and society. The line mainly connects the pumped storage power plants in central and western Austria via Tauern/Kaprun, making it a key east-west link in the APG power grid. The Kaprun–Weißenbach line ensures that electricity from renewable sources goes wherever it is needed. 

Frequently asked questions - FAQ

Frequently asked questions - FAQ

Wie merkt man, dass ein Seil zu alt ist?

Um die Leistungsfähigkeit eines Leitungsseils zu bestimmen wird ein Teil des alten Seils herausgeschnitten und im Labor geprüft. Wenn gewisse Werte nicht mehr erreicht werden, muss das Seil erneuert werden. Ein altes Seil hat nicht mehr die Kapazität, die man benötigt, um eine sichere Stromversorgung für Österreich und die Region zu garantieren.

Was bedeutet der Eingriff für die Betriebssicherheit, Integration Erneuerbare und Kapazität?

Mit der Erneuerung des Leitungsseils wird die volle Leistungsfähigkeit der Leitung und somit eine nachhaltig sichere Stromversorgung in der Großregion Steiermark und Salzburg gewährleistet. Durch den Entfall altersbedingter Betriebseinschränkungen muss künftig auch weniger Engpassmanagement vorgenommen werden.

Ein leistungsstarkes Netz ist Voraussetzung für die sichere Stromversorgung, aber auch für die Integration und Verteilung von erneuerbarer Energie. Die Leitung zwischen dem UW Tauern und dem UW Weißenbach stellt eine wichtige Ost-West-Verbindung im APG-Netz dar, denn sie bindet via Tauern/Kaprun vor allem die Pumpspeicherkraftwerke in Zentral- und Westösterreich an.

Wie sind die Zufahrten geregelt?

Zur Durchführung des Seiltauschs entlang der Trasse war es notwendig, dass die Maschinen und das Baumaterial zu den Masten und der Trasse zufahren und transportiert werden können. Die dafür notwendigen forst- und naturschutzrechtlichen Genehmigungen gab es.

APG ist der Einfluss auf Natur & Mensch ein großes Anliegen, weshalb Baumaßnahmen so schonend wie möglich geplant und umgesetzt werden.