Background
Since the time of commissioning, the European power grid operators have faced significantly increasing challenges: The EU has declared the expansion of renewable energies to a European topic of paramount importance (20-20-20 goals); Austria has also set itself very ambitious targets in this area. Together with the massive expansion of renewable energies and the impacts from market liberalisation, the European power grid operators are facing enormous power flows.
The Burgenland and Styria line will therefore not only have great importance for Austrian supply security in future, but also represent a key prerequisite for the integration of the increasing amounts of renewable energies – and, hence, the required massive expansion of the corresponding electricity generation.
The Burgenland line was commissioned in 1999 and was the first section of the closure in the gap of the 380 kV ring that was so vital for the supply security in the East of Austria. 2009 saw the closing of the 380 kV ring with the commissioning of the Styria line. The supply security in East and South Austria can therefore be guaranteed in the long-term.
Project status
| |
|
| October 2010 |
Approval of high-voltage line standardsA |
| December 2010 |
Approval of environmental standards for Lower Austria |
| March 2011 |
Approval of environmental standards for Burgenland |
| July 2011 |
Beginning of assembly works |
| May 2012 |
Completion of assembly works and recommissioning |