APG - Austrian Power Grid
  • deutsch

Search

    • PORTRAIT & MISSION STATEMENT

    • Strategy
    •  
    • HISTORY

    •  
    • ORGANISATION

    • Supervisory Board
    • Company Management
    •  
    • PROCUREMENT

    •  
    •  
    • FACTS & FIGURES

    •  
    • POWER GRID CONTROL

    •  
    •  
    •  
    •  
    • APG-GRID

    •  
    • GRID PLANNING

    •  
    • EUROPEAN GRID ASSOCIATION

    • TSC
    •  
    •  
    • ASSETS

    • Grid System
    • Operating Regions, Operational Management and Fault Management
    • Maintenance
    •  
    • GRID EXPANSION

    • Network development plan 2011
    • Master Plan
    •  
    •  
    •  
    •  
    • ELECTRICITY MARKET

    • Legal
    • Tariffs
    •  
    • BALANCING

    • Conditions for Participation
    • Control Area Imbalance
    • Primary Control
    • Secondary Control
    • Tertiary Control
    • Unintentional Deviation
    • Statistics
    •  
    •  
    • CROSS-BORDER EXCHANGE

    • Auctions
    • Available Capacities
    • Intraday Capacities
    • Capacity Reductions
    • Effects of Grid Expansion
    • Schedules
    • Rules regarding Schedules
    • Load Flows
    •  
    •  
    • GENERATION

    • Generation Forecast
    • Non-available Capacities
    • Storage Level
    • Eco-electricity
    • Wind Energy
    • Wind Energy Forecast
    • Installed Power Plant Capacity
    •  
    •  
    • LOAD

    • Load Forecast
    • Capacity Margin
    •  
    • GRID LOSSES

    • Tenders
    • Procurement Concept
    • Frequently asked questions
    •  
    •  
    • 380-KV-SALZBURG LINE

    • Project part 1 (St. Peter - Salzburg)
    • Project part 2 (Salzburg - Tauern)
    •  
    • 380 KV LINE ST. PETER - STAATSGRENZE (SIMBACH)

    •  
    • SOUTHERN BURGENLAND - VIENNA SOUTHEAST 380 KV LINE (BURGENLAND LINE)

    •  
    • 380 KV LINE AT DÜRNROHR - VIENNA SOUTHEAST

    •  
    •  
    •  
    •  
    •  
    • NEWS

    •  
    • PRESS RELEASES

    •  
    • DOWNLOADS

    • Pictures
    • Video
    •  
    • POSITION

    •  
    •  
    •  
    •  
    •  

Project part 2 (Salzburg - Tauern)

The Salzburg line Salzburg-Tauern covers a length of 128 km, connecting the newly erected substation of Salzburg with the Tauern (Kaprun) substation, which is to be adapted accordingly. The project also includes the 220 kV connection from the Pongau substation to Wagrain/Flachau.

 

Key data

Total length of new line   131 km 
thereof 380 kV lines  117 km
  thereof 220 kV lines 14 km
Total length of dismantled lines   approx. 250 km
Accompanying 110 kV lines   approx. 36 km
Cabling 110 kV lines   across 30 km 

 

Office Salzburg line

Hauptstraße 73

5600 St. Johann im Pongau

Infohotline: 0800 - 311 380

CONTACT

Hafner

Dipl.-Ing. Wolfgang Hafner

project manager

  • +43 (0)50320-56452
  • wolfgang.hafner@apg.at

CONTACT

Breiter

Dipl.-Ing. Birgit Breiter, MAS

communication

  • +43 (0)50320-51116
  • +43 (0)664-828 64 30
  • birgit.breiter@apg.at
  • 380-KV-SALZBURG LINE
    • Project part 1 (St. Peter - Salzburg)
    • Project part 2 (Salzburg - Tauern)
      • – $name
      • – $name
  • 380 KV LINE ST. PETER - STAATSGRENZE (SIMBACH)
  • SOUTHERN BURGENLAND - VIENNA SOUTHEAST 380 KV LINE (BURGENLAND LINE)
  • 380 KV LINE AT DÜRNROHR - VIENNA SOUTHEAST

© AUSTRIAN POWER GRID AG, 2012

  • Terms of use