APG - Austrian Power Grid
  • deutsch

Search

    • PORTRAIT & MISSION STATEMENT

    • Strategy
    •  
    • HISTORY

    •  
    • ORGANISATION

    • Supervisory Board
    • Company Management
    •  
    • PROCUREMENT

    •  
    •  
    • FACTS & FIGURES

    •  
    • POWER GRID CONTROL

    •  
    •  
    •  
    •  
    • APG-GRID

    •  
    • GRID PLANNING

    •  
    • EUROPEAN GRID ASSOCIATION

    • TSC
    •  
    •  
    • ASSETS

    • Grid System
    • Operating Regions, Operational Management and Fault Management
    • Maintenance
    •  
    • GRID EXPANSION

    • Network development plan 2011
    • Master Plan
    •  
    •  
    •  
    •  
    • ELECTRICITY MARKET

    • Legal
    • Tariffs
    •  
    • BALANCING

    • Conditions for Participation
    • Control Area Imbalance
    • Primary Control
    • Secondary Control
    • Tertiary Control
    • Unintentional Deviation
    • Statistics
    •  
    •  
    • CROSS-BORDER EXCHANGE

    • Auctions
    • Available Capacities
    • Intraday Capacities
    • Capacity Reductions
    • Effects of Grid Expansion
    • Schedules
    • Rules regarding Schedules
    • Load Flows
    •  
    •  
    • GENERATION

    • Generation Forecast
    • Non-available Capacities
    • Storage Level
    • Eco-electricity
    • Wind Energy
    • Wind Energy Forecast
    • Installed Power Plant Capacity
    •  
    •  
    • LOAD

    • Load Forecast
    • Capacity Margin
    •  
    • GRID LOSSES

    • Tenders
    • Procurement Concept
    • Frequently asked questions
    •  
    •  
    • 380-KV-SALZBURG LINE

    • Project part 1 (St. Peter - Salzburg)
    • Project part 2 (Salzburg - Tauern)
    •  
    • 380 KV LINE ST. PETER - STAATSGRENZE (SIMBACH)

    •  
    • SOUTHERN BURGENLAND - VIENNA SOUTHEAST 380 KV LINE (BURGENLAND LINE)

    •  
    • 380 KV LINE AT DÜRNROHR - VIENNA SOUTHEAST

    •  
    •  
    •  
    •  
    •  
    • NEWS

    •  
    • PRESS RELEASES

    •  
    • DOWNLOADS

    • Pictures
    • Video
    •  
    • POSITION

    •  
    •  
    •  
    •  
    •  

Tenders for Procurement of Grid Losses in APG Control Area

Austrian Power Grid AG handles the market procurement of grid losses for most of the transmission grid operators in Austria.

The most important information regarding the procurement of loss energy can be found on this page.

Participation conditions

See Participation Rules for Offerers. All legally binding documents are published under this link.

Tendered products

Yearly, quarterly and monthly products for base and peak times respectively up to 2 years in advance

Volume put out to tender

Mostly several 10s of megawatts per tender; total of approx. 3 TWh per year.

Minimum and maximum bid

The minimum bid is 1 MW. Bids in excess of 1 MW can be submitted in full MW increments. The supplier can bid up to his credit limit.

Tendering platform

The tenders take place exclusively via the electronic tendering platform.

When do the tenders take place?

The bidding period is normally on Thursday from 10:00 to 10:30. Tenders do not take place in December, in the first half of January or when the Thursday falls on a public/church holiday.

Award procedure

At the end of the bidding period the bids are ranked according to prices – starting with the cheapest bids –, until the total volume of power required is reached. These bids are accepted, whereby acceptance of the last (= most expensive) bid may be restricted to ensure that the tender quantity is not exceeded. If the prices of two bids are identical, preference is given to the bid that was placed first.

Suppliers whose offers are successful will receive the price they quoted, i.e. a "pay as bid" approach is adopted.

Schedule processing

A special balance group of APG, which was established specifically to cover grid losses, acts as purchaser on the market. For suppliers of loss energy, whose offer was accepted during the tender procedure, this is a standard electricity supply transaction. APG handles the further distribution of energy to operators of grids in which losses occurred by way of schedules.

LINKS

  • Tendering Platform
  • Results of the Tenders
  • Next Tenders

DOWNLOADS

  • Calendar of Tenders

CONTACT

Electricity Procurement

Inquiries regarding procurement of grid loss energy

  • +43 (0)50320-56477
  • frontoffice.sdl@apg.at
  • ELECTRICITY MARKET
    • Legal
    • Tariffs
  • BALANCING
    • Conditions for Participation
    • Control Area Imbalance
    • Primary Control
    • Secondary Control
    • Tertiary Control
    • Unintentional Deviation
    • Statistics
  • CROSS-BORDER EXCHANGE
    • Auctions
    • Available Capacities
    • Intraday Capacities
    • Capacity Reductions
    • Effects of Grid Expansion
    • Schedules
    • Rules regarding Schedules
    • Load Flows
  • GENERATION
    • Generation Forecast
    • Non-available Capacities
    • Storage Level
    • Eco-electricity
    • Wind Energy
    • Wind Energy Forecast
    • Installed Power Plant Capacity
  • LOAD
    • Load Forecast
    • Capacity Margin
  • GRID LOSSES
    • Tenders
      • – Participation Rules
    • Procurement Concept
    • Frequently asked questions

© AUSTRIAN POWER GRID AG, 2012

  • Terms of use